Roosevelt Pond

CIVIL & SITE DESIGN »

Type: Water Body Rehabilitation
Location: Roosevelt, New York
Client: Nassau County Department of Public Works
Completion Date: 2008
Construction Cost: $2,000,000

This project consisted of improvements to Roosevelt Pond and the surrounding park. The project consisted of:

  • Preparation of environmental study &master plan for improvements to pond, adjacent park & inflow streams.
  • ncorporated GIS mapping into project base-mapping.
  • Perform a field reconnaissance and environmental inventory.
  • Replacement of timber bulkhead.
  • Maintenance and Protection of Traffic
  • .

  • Developed conceptual construction sequence.
  • Improvement / replacement of park amenities.
  • Perform topographic survey of pond and park.
  • Evaluated measures to reduce water fowl access to ponds.
  • Pond sediment and water quality testing.

Responsible for the preparation of project study, preliminary and final design plans, specifications and construction cost estimate, securing permits from regulatory agencies, bid evaluation, shop drawing review and construction support services. This project was completed on time and within budget.